assignment代写

英国代写论文:业主的损失补救

英国代写论文:业主的损失补救

如果在工程建设中出现的问题是承包商方面的问题,业主有权在各种损害理论下寻求补救。从一般意义上讲,对于因承包人违约而延误给业主造成的相应损害,适用下列损害赔偿主张:因无法及时获得已建成的设施而造成的收入损失。由于新地点的准备工作出现延误,导致新设施无法使用。由于完工较晚,整个设备的价值正在下降。所提供的案件可与要求损害赔偿有关,即由于完全建造的设施的供应延迟而造成收入损失。正如本案所提到的,黄某向Bill详细说明了完成日期,但并没有说明关键原因,也没有消除紧迫感。进一步说,比尔没有按时完成施工。由于Bill这部分的延误,导致该建筑没有按照规定的期限按时建造,Huang在提供部件的投标中失败,面临损失。


英国代写论文:业主的损失补救
因此,Bill对Huang所面临的损失负责,而Huang有权要求赔偿由于完全建成的设施的可用性延迟造成的收入损失,损失金额为150,000美元。因违反合同而造成的损失,可以提出索赔。能否按时完成大型建设项目,取决于几个行业和承包商工作的衔接和顺序是否正确。正如谚语所说,时间与金钱有着直接的联系,当项目偏离了关键的路径时,延迟以及试图重新获得进度的延误最终会改变时间并破坏成本估算,进一步导致组织蒙受损失。同样,如果从合同之日起错误地延长履行期限,业主也可能因迟延履行而遭受损失,然后提起追偿损害赔偿金的诉讼。由于建筑师、业主或任何其他承包商的过失,承包商可能会提出延期索赔,要求收回施工现场的额外成本,超出预计时间。

英国代写论文:业主的损失补救

If the fault turns out to be from the side of contractor in constructing the project on time, the owner will have the right of seeking redressal under various theories of damage. In the general sense, the consequential damages for the owner arising due to delay by a defaulting cover of contractor, the following claims of damages are applicable:Extended costs of contract administration and inspection.Loss of revenue as a result of delay in the availability of fully constructed facilities.Loss of utilization of new facility for retention as there was delay in preparing the new place on time.Value of the complete facility being diminished because of the late completion.The case provided can be related with the claim of damage for the loss of revenue as a result of delay in the availability of fully constructed facilities. As mentioned in the case, Huang specifies the date of completion to Bill, without stating the key reason behind, yet not eliminating the sense of urgency. Further ahead, Bill does not complete the construction on time. Due to this delay from the part of Bill, the building is not constructed on time as per the deadline fixed, and Huang faces a loss as he loses the tender for supplying the components.


英国代写论文:业主的损失补救
Therefore, Bill is liable for the losses faced by Huang and Huang has the right of claiming the damages for the loss of revenue as a result of delay in the availability of fully constructed facilities that is accounted at 150,000 dollars. Damages for breach of contract in context with schedule can be claimed. Completing large projects of construction on time is dependent on the correct interfacing and sequencing of the work of several trades and contractors. With the passage of adage, time has a direct implication with money, and when there is straying of project from the crucial path, delays along with attempts on regaining slippage of schedule end up altering time and foiling estimates of cost, further causing the organizations for incurring losses. In the same way, when there is wrongful extension of performance from the date of contract, losses may be sustained by the owner as a result of delay, followed by the introduction of suit for the recovery of the damages. There can be filing of delay claims by the contractors for recovering the extra costs underlying the performance of job site more than the time estimated because of the fault from the side of architect, owner or any other contractor.